🗞️ Why in News The Cabinet Committee on Economic Affairs (CCEA), chaired by Prime Minister Narendra Modi, approved the Second Container Terminal at Kamarajar Port Limited (KPL) under the Public Private Partnership (PPP) mode on a Design, Build, Finance, Operate and Transfer (DBFOT) basis, at an estimated cost of Rs 4,288.26 crore including GST, PIB said on 25 November 2026. The 900-metre terminal is to handle 2.0 million TEUs a year, in two phases.
The Project: What the CCEA Approved
PIB describes “a 900-metre-long container terminal with a design draft of 18 metres and an annual container-handling capacity of 2.0 million Twenty-foot Equivalent Units (TEUs), to be implemented in two phases.”
| Feature | Second Container Terminal, Kamarajar Port |
|---|---|
| Mode | PPP, on a DBFOT basis |
| Estimated cost | Rs 4,288.26 crore, including GST |
| Phase I | Rs 2,429.32 crore; 1.1 million TEUs |
| Phase II | Rs 1,858.94 crore; 0.9 million TEUs |
| Terminal | 900 metres long; berth width 30 metres; design draft 18 metres |
| Ships it can take | vessels of up to 24,346 TEUs and 400 metres in length overall |
| Capacity | 2.0 million TEUs a year |
| Dredging | estimated Rs 450 crore, to be borne by KPL |
| Expected jobs | about 750 during construction, about 800 during operations (PIB’s estimate) |
“The investment is to be arranged by the selected concessionaire under the DBFOT model,” PIB said, and “There will be no financial implication for the Government of India”. The dredging cost of Rs 450 crore is indicated separately in the proposal and falls on KPL.
Why a Second Terminal: Demand and Capacity
The existing terminal is nearly full. It has an installed capacity of 0.8 million TEUs a year and handled about 0.7 million TEUs in FY2025-26, “representing utilisation of about 88%”. In all, KPL handled 49.08 million tonnes of cargo and 1,008 vessels in FY2025-26, including more than 7 lakh TEUs of containers.
Traffic is growing faster than the national rate. India’s container traffic grew at a compound annual growth rate (CAGR) of about 7% over the last five years, PIB said, and KPL’s at about 9.9% over the same period.
The hinterland. Demand comes from containerised export-import (EXIM) cargo of the Chennai-Ennore industrial and economic region and the wider southern hinterland, led by automobiles and auto components, engineering goods, electronics and chemicals. PIB names industries and original equipment manufacturers in Tamil Nadu, Karnataka, Andhra Pradesh and Telangana as users.
Bigger ships, fewer transfers. The project, PIB said, will “facilitate direct calls by mainline vessels and reduce dependence on foreign deep-water hub ports and associated feedering costs”. PIB expects the project to strengthen KPL’s position “as a container gateway on India’s East Coast”, in line with Maritime India Vision 2030 and Maritime Amrit Kaal Vision 2047.
How the PPP Works: DBFOT and the 40-Year Concession
The second terminal in numbers
Covers the terminal, its two phases, the 40-year concession and who pays for what.
The concessionaire will be chosen through “a transparent, open global bidding process”. It “will arrange the required financing and recover its investment through user charges in accordance with the provisions of the Concession Agreement and applicable tariff framework”.
The concession period is 40 years, including a construction period of 48 months, counted from the Date of Award of Concession:
- Phase I is scheduled for completion within 24 months of the award, with commercial operations from the 25th month;
- Phase II will be built from the 25th to the 48th month, with full commercial operations from the 49th month.
The bid has not yet been held, so no concessionaire has been named and the 48-month clock has not started.
Kamarajar Port: The Port Itself
Kamarajar Port, “formerly known as Ennore Port Limited”, is one of India’s Major Ports. PIB describes it as “wholly owned by Chennai Port Authority under the Ministry of Ports, Shipping and Waterways”. It lies on the East Coast about 24 km north of Chennai, in Tamil Nadu, on about 2,800 acres of the Coromandel Coast, and its own page gives the port’s handling capacity as 58.44 MMTPA.
In FY2025-26 KPL recorded revenue of about Rs 1,280 crore and a Profit Before Tax of Rs 924 crore, and its cargo has grown at a CAGR of 13.64% over the last five years, PIB said. Kamarajar Port’s chair is among the Major Port chairs named in Ujiyari’s piece on the Maritime State Development Council and the Indian Ports Act, 2025.
Background. Maritime India Vision 2030 was launched in 2021 by the Prime Minister at the Maritime India Summit 2021, which he inaugurated on 2 March 2021; it lists over 150 initiatives covering 515 key activities across 10 themes. On the west coast, Kerala’s Vizhinjam, which PIB in 2025 called the “country’s first dedicated container transshipment port”, is meant to “reduce reliance on foreign ports for cargo transshipment”.
Map Work: Kamarajar Port and the Coromandel Coast
Map 1: Kamarajar Port, north of Chennai
Kamarajar Port on the Coromandel Coast
Covers Kamarajar Port, Kattupalli, Chennai Port, Pulicat Lake and the Tamil Nadu-Andhra Pradesh border.
Places to mark
| Place | Where it is | Why it is in this story |
|---|---|---|
| Kamarajar Port | Tamil Nadu, East Coast, on the Bay of Bengal, about 24 km north of Chennai | site of the Second Container Terminal |
| Ennore | Tamil Nadu coast, just south of Kamarajar Port | the port’s former name: Ennore Port Limited |
| Kattupalli | Tamil Nadu coast, north of Kamarajar Port | site of a neighbouring port, Adani Kattupalli Port |
| Chennai Port | Chennai, south of Kamarajar Port | Chennai Port Authority wholly owns KPL, PIB says |
| Pulicat Lake | a lagoon on the Tamil Nadu-Andhra Pradesh border, north of the port | marks the Tamil Nadu-Andhra Pradesh border north of the port |
| Coromandel Coast | the East Coast of Tamil Nadu on the Bay of Bengal | the port’s coastline |
| Andhra Pradesh | north of Tamil Nadu | part of the port’s hinterland, PIB says |
| Karnataka and Telangana | inland States of south India | part of the port’s hinterland, PIB says |
Map facts
- Kamarajar Port is on the Coromandel Coast of the Bay of Bengal, about 24 km north of Chennai.
- Pulicat Lake straddles the border: a major part lies in Andhra Pradesh’s Tirupati district and the rest in Tamil Nadu’s Thiruvallur district.
- Neighbouring ports: Kattupalli lies to the north of Kamarajar Port and Chennai Port to the south.
- Hinterland named by PIB: Tamil Nadu, Karnataka, Andhra Pradesh and Telangana.
Mains Lens
Why it matters.
- Capacity before congestion. With the existing terminal at about 88% utilisation and traffic growing at about 9.9% a year, a terminal of 2.0 million TEUs a year comes on top of the existing 0.8 million.
- Direct calls. An 18-metre draft and vessels of up to 24,346 TEUs aim at direct calls by mainline ships, cutting dependence on foreign hub ports and feedering costs.
- PPP with no central outlay. The concessionaire funds the terminal and recovers it through user charges; the public side bears the Rs 450 crore dredging cost through KPL.
- Manufacturing link. Autos, electronics and engineering goods from the southern States need a nearby container gateway.
Issues to watch.
- Bidding risk. The project depends on attracting a concessionaire on fair terms through open global bidding.
- Tariffs. Revenue comes from user charges under the tariff framework, so tariffs decide whether the terminal stays competitive.
- Time. Full operations come only from the 49th month after award.
- Coast and wetlands. The port sits on a coast with Pulicat Lake to its north, so dredging and construction need careful environmental management.
Way forward. Run a transparent bid, keep the concession terms stable, and link the terminal to rail and road corridors serving the hinterland. Next, the global bidding is to be held and the concession awarded; Phase I is to begin commercial operations in the 25th month after the award.
UPSC Relevance
GS Paper 3: infrastructure (ports); investment models (PPP, DBFOT); logistics and EXIM trade. GS Paper 1: locating Kamarajar Port, Chennai Port and Pulicat Lake on the Coromandel Coast. Prelims: the terminal’s cost, capacity, draft and phases; DBFOT; KPL’s former name and status; the Major Port Authorities Act, 2021; Maritime India Vision 2030.
📌 Facts Corner, Knowledgepedia
Prelims, statement-ready facts:
- Approval: CCEA, Second Container Terminal at Kamarajar Port Limited (KPL); PIB, 25 November 2026.
- Mode: Public Private Partnership on a Design, Build, Finance, Operate and Transfer (DBFOT) basis.
- Cost: Rs 4,288.26 crore incl. GST = Rs 2,429.32 crore (Phase I) + Rs 1,858.94 crore (Phase II).
- Capacity: 2.0 million TEUs a year = 1.1 million (Phase I) + 0.9 million (Phase II).
- Terminal: 900 m long; berth width 30 m; design draft 18 m; vessels up to 24,346 TEUs and 400 m long.
- Concession: 40 years including 48 months of construction; Phase I operations from month 25, full operations from month 49.
- Dredging: about Rs 450 crore, borne by KPL; no financial implication for the Government of India.
- KPL in FY2025-26: 49.08 million tonnes of cargo, 1,008 vessels; existing terminal 0.8 million TEU capacity, about 88% used.
- KPL: formerly Ennore Port Limited; first corporatised Major Port; landlord port model; about 24 km north of Chennai.
- Major Port Authorities Act, 2021: Act No. 1 of 2021; assent 17 February 2021; replaced the Major Port Trusts Act, 1963.
- Maritime India Vision 2030: launched at the Maritime India Summit 2021; over 150 initiatives, 515 key activities, 10 themes.
Prelims, the traps:
- Approved is not built: bidding is still to come, and the 48 months run from the Date of Award of Concession.
- 49.08 million tonnes is KPL’s cargo handled in FY2025-26; its handling capacity, per KPL, is 58.44 MMTPA.
- The concessionaire funds the terminal, but KPL bears the Rs 450 crore dredging cost.
- Kamarajar Port was formerly Ennore Port; it is not the same as Chennai Port, which lies to its south.
Mains, arguments and keywords:
- Keywords: landlord port; DBFOT; concession agreement; user charges; mainline vessels; feedering costs; EXIM hinterland.
- Deep-draft terminals let mainline ships call directly and cut dependence on foreign hub ports.
- Way forward: transparent bidding, stable concession terms and rail and road links to the southern hinterland.
Interview, be ready for:
- “Why build through PPP and not public money?” Answer: the concessionaire funds and runs it and recovers costs through user charges, so the Centre bears no outlay; regulate tariffs.
- “Why does India need deep-draft container terminals?” Answer: they allow direct calls by mainline vessels and reduce reliance on foreign hubs and feedering.
Sources: PIB, CCEA approves Second Container Terminal at Kamarajar Port, 25 November 2026; Kamarajar Port Limited; Ministry of Ports, Shipping and Waterways; Major Port Authorities Act, 2021; PPP India, glossary; PIB, Maritime India Vision 2030; PIB, Vizhinjam port, 2025